Optimized plant reliability and availability by close collaboration between Valmet and Eneco Bio Golden Raand Delfzijl
Summary
Location | Eneco Bio Golden Raand Delfzijl, Netherlands |
Customer challenge | Insufficient fuel quality and unreliable plant operation |
Solution | Annual inspections of main equipment with performance evaluation and maintenance recommendations. Process and operation support. 24/7 on-call service, and outage planning. |
Result | Optimized plant reliability and availability with overall plant efficiency higher than anticipated. |
Technical summary - Valmet CFB boiler, Bag House Filters and ESP
Start-up date | 2013 |
Steam | 127 MWth, 50 kg/s, 90 bar, 520 °C |
Fuels | Recycled wood |