Special transportations for Metsä Fibre’s Kemi bioproduct mill travelled through downtown Kemi

Nov 25, 2021

Nine Valmet Continuous Cooking digester and ImpBin components were transported to the Kemi bioproduct mill site though downtown Kemi in late October – early November, 2021.

November is generally quite dark time in Finland, and it has been even darker in the city center of Kemi. The street lighting had to be temporarily removed because all space was needed for transporting nine huge cooking digester and ImpBin components from inland harbor to the Kemi bioproduct mill project site. Each component was transported separately and during the evening to cause minimum inconvenience to other traffic.

Downtown Metsä logo 570x277.jpg

A large number of people witnessed the first component being transported through downtown Kemi on October 29. It proceeded at walking speed along the four-kilometer route, taking around four hours. In total, it took about two weeks for all nine components to be at the site.

The longest component was 35 meters long, the widest 14 meters wide and the heaviest one weighted 275 tonnes. They arrived in Kemi from China by a charter vessel. In Kemi they were transported by barge from the deep-water port of Ajos to Kemi’s inland port, from which they were transported to the site by truck.

kemi harbour 570x277.jpg

“Components are normally transported directly from the Ajos harbor to the site by truck, weight limitations meant this route was not possible for these components. A detailed two-year planning ensured everything went smoothly in the transportation,” tells Janne Lehtomäki, Valmet’s Site Logistics Supervisor.

mill arrival 570x277.jpg

Project well on track

“The project is on track for a start-up in the third quarter of 2023. Engineering and procurement are almost finalized, and manufacturing is going ahead at full speed. Civil works continue at the site. We have also started erection works, and deliveries to the site are ongoing,” says Risto Hokajärvi, Valmet’s Project Director.

“Pulp tower preassembly has been ongoing at the site since July and now that the digester and ImpBin components are hauled to the site the lifting has started. We have currently over a dozen Valmet employees at the site and our activities at site will start ramping up fast at the beginning of 2022, when the remaining six process areas will initiate their site mobilization,” Valmet’s Site Manager Antti Ahola summarizes the project’s current status.

 

Anttti Ahola 570x277.jpg

Antti Ahola at the Kemi project site (Photo: Metsä, photographer: Nina Susi)

 

 

Metsä Fibre Kemi bioproductmill project in a nutshell

Totalling EUR 1.6 billion, the investment in Metsä Group’s Kemi bioproduct mill is the largest in the history of the Finnish forest industry. An estimated 15,000 separate persons will be working during the construction phase.

Valmet is delivering the full production process from wood handling to baling, designed to produce both softwood and hardwood pulp, as well as the automation system for the whole mill, including features from Valmet’s Industrial Internet (VII) offering. The project also includes a rebuild of the existing fiberline.

Check the site’s current situation on Metsä’s web cameras