Valmet delivers major pressure part replacement for Eneco’s biomass plant in the Netherlands to increase reliability
Valmet Oyj’s trade press release on July 7, 2026, at 9:30 a.m. EEST
Valmet will deliver a new secondary superheater to the circulating fluidized bed (CFB) boiler at Eneco’s Bio Golden Raand biomass plant in Delfzijl, the Netherlands. The service project supports Eneco and Valmet’s lifecycle partnership by reducing the risk of unplanned downtime and improving the plant’s overall reliability.
“Maintaining high availability is critical for reliable baseload steam supply to our customers. Lifecycle replacements like this secondary superheater are key to securing reliable performance both now and in the future. Our long-standing partnership with Valmet ensures that upgrades are planned and executed proactively, minimizing risks to production. We value Valmet’s technical expertise and strong understanding of our plant, which supports efficient execution and our long-term performance targets,” says Tom Schepers, Head of Industrials at Eneco.
The CFB boiler was originally delivered by Valmet in 2013. The combined heat and power plant uses recycled wood as fuel to produce renewable electricity for the local community and steam for an industrial plant.
“Eneco’s Bio Golden Raand plant is a great example of how efficient and sustainable energy production can be achieved with demanding fuels through continuous development. The secondary superheater replacement is a key lifecycle investment that helps to ensure high availability and reliable production. By combining our service expertise with the plant’s operational knowledge, we deliver solutions that minimize downtime and support stable and efficient performance,” says Oliver Sarelin, Sales Manager, EMEA, Pulp, Energy and Circularity, Valmet.
The order is included in Valmet’s orders received for the second quarter of 2026. The value of the order is not disclosed. The delivery and installation will take place in March 2027.
One-to-one replacement enables seamless boiler integration
The delivery includes a turn-key replacement of the CFB boiler’s secondary superheater, covering engineering, manufacturing, and installation. The new superheater is designed as a one-to-one replacement, enabling seamless integration with the existing boiler and minimizing installation time during the planned outage. The scope also includes installation by Valmet’s own service team, supporting efficient execution and high quality.
About the customer Eneco
Eneco is a Dutch energy company operating the Bio Golden Raand biomass plant in Delfzijl, the Netherlands. The plant produces steam and electricity for industrial use and is characterized by high availability requirements, typically operating for around 8,000 hours per year. Valmet and Eneco have a long-term service agreement and continuous partnership focused on maintaining reliable and efficient plant performance.
VALMET
Corporate Communications
For further information, please contact:
Oliver Sarelin, Sales Manager, EMEA, Pulp, Energy and Circularity, Valmet, tel. +358 400 468 239
Valmet is a global technology leader in serving process industries. We work with our customers throughout the lifecycle, delivering cutting-edge technologies and services, as well as mission-critical automation and flow control solutions. Backed by more than 225 years of industrial experience and a global team of 18,500 professionals close to customers, we are uniquely positioned to transform industries toward a regenerative tomorrow.
In 2025, Valmet’s net sales totaled approximately EUR 5.2 billion. Our head office is in Espoo, Finland, and we have experts in approximately 40 countries around the world. Valmet’s shares are listed on Nasdaq Helsinki.
Follow us on valmet.com | X | LinkedIn | Facebook | YouTube | Instagram | Instagram (IR)